Colleagues, you are invited to download and use the project schedule in MS Project Pro. In the schedule developed:
- The list of tasks for the construction of the cottage. Developed a two-tier structure WBS.
- Developed a financing plan with a budget from the investor
- Developed a plan for the participation of contractors on two overall project objectives
- A work plan has been developed for brigades, with three brigades reporting volumes and one is calculated in cash.
- Planned material resources. Some materials are planned with the indication of volumes. Cost resources are planned for consumable planning and molding.
| Name of the project | Construction of a two-storey cottage and arrangement of a site |
| Duration | 169 days |
| Costs | $ 272 000 |
|---|---|
| Description of the project |
Project participants
| Group | Interested party |
|---|---|
| Customer | Physical / Legal entity |
| Developer | Company Developer |
| Сontractors | Roof installation company |
| Greening company |
Purpose and products of the project
Construction of a two-storey cottage and arrangement of a site
Top-level tasks
| Task title | Duration | Costs |
|---|---|---|
| Foundation installation | 28 days | $26 462,50 |
| Frame installation | 63 days | $94 730,00 |
| Windows installation | 26 days | $32 090,00 |
| Installation of the roof | 43 days | $54 400,00 |
| Facade device | 40 days | $54 310,00 |
| Land improvement | 81 days | $9 710,00 |
Contractors
| Types of contractors | Works |
|---|---|
| Roof installation company | Trussing system installation |
| Arrangement of the vapor barrier layer | |
| Stacking of insulation materials | |
| Construction of waterproofing layer | |
| Roof insulation with screed | |
| Metal roofing | |
| Mantling of ventilation shafts and installation of a visor | |
| Landscaping company | Territory planning |
| Arrangement of sidewalks, access roads to the garage | |
| Landscaping of the site | |
| Enclosure of the site |