Логотип компании Oberemok&Co
Main / Planning regulations

Resource Planning Rules in MS Project

Фото информации

Recommendations for the development of the project schedule in MS Project Professional to EPM configuration "Resource Management" effektino solve resource conflicts in the project and reduce the time and costs of the project.

1. Assign resources only to regular project tasks

Meaning: resources (people) must be assigned to regular tasks rather than summary tasks, calendar tasks, or milestones. This ensures correct calculations of Work, Duration, and Cost.
MS Project practice: summary tasks aggregate data “from below,” so assigning resources directly to them distorts resource load and project metrics.
Example:
Simplistic: assign an engineer to the summary task “Installation.”
Correct: assign the engineer to “Cable‑tray installation,” “Cable laying,” “Cabinet connection.”

2. It is recommended to assign only one resource to each task

Meaning: one execution owner reduces managerial uncertainty — who reports progress, who updates % complete, and who is responsible for deadlines.
When it can be different: if the work can truly be performed in parallel (e.g., two installers working in different zones), it is better to split the task into two rather than mix two people in one activity.
Example:
Problematic: “Room finishing (2 resources)” — one reports 80%, the other 20%, resulting in incorrect totals.
Clear: “Finishing — Block A (Resource 1)” and “Finishing — Block B (Resource 2).”

3. Assign resources at 100% workload (by default)

Meaning: the basic norm is full availability for the task, which simplifies calculations. Exceptions (50%, 25%) should be intentional — for example, when a person works in parallel on other tasks or their role normally assumes part‑time involvement (e.g., an architect‑consultant at 25%).
MS Project practice: when the assignment is <100%, the duration will increase for the same amount of work (Work). This affects the critical path. You must understand task types (Fixed Units/Work/Duration) and the “Effort‑Driven” rule.
Example:
Baseline: analyst assigned to “Requirements gathering” = 100%.
Intentional exception: expert assigned to “Reviewing” = 25%, duration increases proportionally.

4. Only one responsible person can be assigned to a task or summary task

Meaning: besides performers, there must be a single Responsible/Owner to maintain clarity about who makes decisions, removes blockers, and approves changes.
Practice: even if multiple resources are assigned to a task, the “Responsible” role remains unique.
Example:
Three engineers work on “Commissioning,” but only one is responsible — the lead site engineer.

5. A responsible person can be assigned to both tasks and summary tasks

Meaning: at the operational level, the responsible person oversees a specific task; at the WBS (summary task) level, the responsible person acts as the curator for an entire work package.
Practice: this establishes a clear management hierarchy from micro‑tasks to large work packages.
Example:
Task “Interface testing” — Responsible: “QA Lead.”
Summary task “Communication System” — Responsible: “Head of Communications Department.”

6. It is recommended to store the responsible person in a custom Text field

Meaning: keeping the “Responsible” separately from resource assignments simplifies reporting, filtering, analytics, and exporting. A custom field (Text1/Text2 renamed to “Responsible”) prevents confusion between the person performing the work and the person responsible for the result.
MS Project practice:

  • Rename the field Text1 → Responsible.
  • Enter the full name/role of the responsible person (not necessarily the same as the assigned resource).
  • Build filters/groupings “by Responsible” and generate reports with a single click.
    Example:
    Task has a resource “Electrical engineer (Ivanov)” but the Responsible field shows “Petrov A.A. (Department Head).” Petrov oversees the work; Ivanov performs it.
Настройка Microsoft Project Server 2010 для компании «XXI Век»
Внедрение КСУП на базе MS Project Server 2013 для ООО
Внедрение КСУП на Богучанской ГЭС для компании
Внедрение КСУП на базе MS Project Server в
Проект модернизации налоговой службы Украины
Внедрение КСУП на базе MS Project 2013 ТОВ
Внедрение КСУП на базе Microsoft Project Server 2013 в компании BI Group
Внедрение КСУП в ПАТ «Домостроительный комбинат №4»
Внедрение КСУП на базе MS Project Online в компании «Архиматика»
Внедрение КСУП на базе MS Project Online для ООО
Развитие системы управления проектам для общественной организации «Объединение ответственных граждан»
Проект внедрение КСУП в девелоперской компании «Інтергал‑Буд» на базе Microsoft Project Online.
Внедрение инструментов проектного управления в компании «DEZEGA Holding Ukraine»
Внедрение инструментов проектного управления в компании «СТРУКТУМ»
Внедрение проектного управления в компании «Хорос» на базе MS Project Pro и MS Project Online
Внедрение инструментов проектного управления в компании «Новос Девелопмент»