The process of developing a corporate project management system supports the development of corporate document templates and project schedule. The basis for the development of management systems are the results of the implementation of the portfolio companies. The result of the implementation of this process are the rules of project management templates schedules and templates of the project documents. Responsible for the implementation of this process is the specialist responsible for project management in the company or the head of the project office.

Elements of the corporate system, that change:

  • Regulations corporate project management system
  • Project Documentation Templates
  • The structures used in the system (the structure of the portfolio, WBS structure of the high-level design, RBS resource structure, CBS structure contracts, OBS organizational structure)
  • Register of corporate quality standards and corporate risk register of the company.
  • Performances information system MS Project Professional
  • Performances Information System MS Office 365

For any level of the project management system is implemented the following sequence of operations:

  1. During the implementation of the project portfolio Project Office experts analyze the results of the management of projects.
  2. The result is a proposal to amend elements of corporate project management systems.
  3. At the end of the implementation period (over the weekend) held meeting of the group of EPM. This group may include: project managers, project managers, project office experts, leading specialists in the subject field.
  4. As part of the meeting held coordination developed changes.
  5. All agreed changes are submitted for approval by the company's management.
  6. Following approval, changes are made to the relevant elements of the project management system.

Business process development of EPM

Business process development of EPM configuration quality and Risk management

Рис.1. Business process development of EPM configuration "Quality and Risk management"


Description of functions of the development process templates schedules

Develop a plan for top-level

Responsible

Portfolio analytic

Incoming documents

Pattern of the schedule

Outgoing documents

Plan top level

Administrator portfolio together team members of the project management system develops hierarchical decomposition of the project, while defining the project life cycle. They set the key objectives of the project and generates the target plan for the project.
In the software product project management MS Project is given:
WBS structure of the project, the key objectives of the project, the restrictions on the key objectives of the project.

Develop a technology roadmap

Responsible

Portfolio analytic

Incoming documents

Plan top level

Outgoing documents

Technological schedule

In the process of detailing and clarifying the content of the project co-manager portfolio Chelny group of project management system develops technological project plan, which expresses the company's technology projects.
In developing the technology plan forms the list of objectives of the project are established communication and duration.
In the software product project management MS Project is given:
It describes the objectives of the project, sets limits on the problem, establishes a link between tasks.

Develop a plan of interaction

Responsible

Portfolio analytic

Incoming documents

Technological schedule

Outgoing documents

Engagement Plan

Based on the analysis of typical stakeholder group of the project management system formed the task of stakeholder engagement. Based on the analysis of problems and results of the project formed the plan document management.
In the software product project management MS Project is given:
The list of tasks in the interaction, and also points to the custom columns in the result document the project objectives.

Assigning types of resources to project tasks

Responsible

Portfolio analytic

Incoming documents

Technological schedule

Outgoing documents

Resource plan

Administrator portfolio together with members of the development project management system determines a list of types of resources required for the project, then these types of resources are assigned to project tasks. The appointment process is determined by the number of required resource types and resolves resource conflicts that have arisen in the appointment of resource types.
In the software product project management MS Project is given:
Description of the types of resources and resource types in the appointment of the project objectives.

Development of lots

Responsible

Portfolio analytic

Incoming documents

Technological scheduleResource plan

Outgoing documents

Lots of project

Administrator portfolio together with members of the development project management system determines the list of tasks for the implementation, which should involve contractors. After that, these tasks are divided into lots of the project,
In the software product project management MS Project:
Defines the list of objectives of the project included in the lots and allocates them with customizable columns.

Development of the project budget

Responsible

Portfolio analytic

Incoming documents

Resource plan

Outgoing documents

Plan costs (budget) project

On the basis of the cost of the resource types used in the project and the volume of their group assignment of project management system determines the cost of the project and form its budget.
In the software product project management MS Project:
Updates tasks and project resources in the project schedule.

Updating the corporate register of quality

Responsible

Project portfolio analyst

Incoming documents

Technological scheduleResource planPlan costs (budget) projectLots of project, Corporate register of quality

Outgoing documents

Portfolio analytic

Analyst portfolio of projects with quality managers analyze the quality requirements of stakeholders of the projects, as well as the implementation of the tasks effektinost on quality control. If the analysis is generated new challenges for quality control analyst portfolio updates the register of corporate quality.
In MS Project: being checked problems with the quality of the project management plan.

Updating the corporate risk register

Responsible

Portfolio analytic

Входящие документы

Technological scheduleResource planPlan costs (budget) projectLots of projectRisk management planCorporate risk register

Outgoing documents

Corporate risk register

Analyst portfolio together with the risk managers analyze the efficiency of the implementation of measures to prevent the occurrence of risk events. Comparing the value of baselines up to the actual portfolio analyst looking deviations in timing, costs and labor costs. Analyzing the results of deviation held initiation and description of risk events affecting projects

In MS Project: Updates tasks and project resources in the project schedule.

Allegations template

Responsible

Portfolio analytic

Incoming documents

Technological scheduleResource planEngagement PlanPlan costs (budget) projectLots of project

Outgoing documents

Pattern of the schedule

After making all the elements in the schedule of the portfolio manager coordinates all its project managers implementing these types of projects. After that maintains the pattern at the head of the project portfolio and puts it on the server for shared use.

Фото автора статьи Oberemok Ivan

Author:

Oberemok Ivan

Trainer and consultant, PhD Project Management, a certified IPMA LEVEL (B), provides training in project management and the use of MS Project, consults on project management

Настройка Microsoft Project Server 2010 для компании «XXI Век»
Внедрение КСУП на базе MS Project Server 2013 для ООО
Внедрение КСУП на Богучанской ГЭС для компании
Внедрение КСУП на базе MS Project Server в
Проект модернизации налоговой службы Украины
Внедрение КСУП на базе MS Project 2013 ТОВ
Внедрение КСУП на базе Microsoft Project Server 2013 в компании BI Group
Внедрение КСУП в ПАТ «Домостроительный комбинат №4»
Внедрение КСУП на базе MS Project Online в компании «Архиматика»
Внедрение КСУП на базе MS Project Online для ООО
Развитие системы управления проектам для общественной организации «Объединение ответственных граждан»
Проект внедрение КСУП в девелоперской компании «Інтергал‑Буд» на базе Microsoft Project Online.
Внедрение инструментов проектного управления в компании «DEZEGA Holding Ukraine»
Внедрение инструментов проектного управления в компании «СТРУКТУМ»
Внедрение проектного управления в компании «Хорос» на базе MS Project Pro и MS Project Online
Внедрение инструментов проектного управления в компании «Новос Девелопмент»